Projects

Creation of new man-made area of ground in the area of Krestovskiy Island territory

Customer: Inteks LLC

Hydraulic fill map: 15 141.23 m3

Types of works:
  • Hydraulic fill
  • Construction of temporary berthing facilities from tubes
  • Geodetic survey

The project under creation of new man-made area of ground in the western part of Krestovskiy Island has been considered and implemented by SILQ Engineering for siting of the new construction underground station “Novokrestovskaya” and facilities, necessary for staging of World Cup in 2018.

The company has executed full set of works from concept creation to its implementation.
Land reclamation
Made on
Tilda